If you are weighing a hotel, villa or rental near Manuel Antonio, the question is whether a new airport makes the property worth more. On 23 October Costa Rica’s transport ministry ordered work to start on the Quepos airfield, a project the government puts at more than ₡6,000 million and describes as a way to attract private jets. We explain what that can change in your numbers, what it cannot, and why you should price the finished airport, not the announcement.
Key takeaways
- Work on the first phase was ordered on 23 October, but the passenger terminal that would serve ordinary visitors has not yet gone to tender and is not expected before late 2028.
- Reports disagree on timing and the budget has grown since September, so we suggest underwriting the slower date and the smaller benefit.
- Private-jet access serves a narrow, high-spend guest, and we found no published data linking it to occupancy or property values around Quepos.
What happened
This piece is written mainly for expat and international buyers of hotels, villas and rentals in the Central Pacific, and secondarily for current property owners there. The airfield in question is La Managua, a small airstrip that serves Quepos and Manuel Antonio.
- On 23 October 2026 the transport ministry (MOPT) ordered works to begin on a new aircraft apron, meaning the paved parking area, of 9,450 square metres with room for nine small aircraft and one helicopter. La Nación reports its cost at ₡2,103 million, with about one year to build.
- Phase two is a passenger terminal of more than 1,000 square metres at ₡4,000 million. La Nación says the tender is expected around November 2026, construction in the second half of 2027 and completion in late 2028.
- The government’s total is now described as more than ₡6,000 million. In late September the transport minister put it above ₡5,000 million, according to Infobae and the Tico Times.
- Sources disagree on timing: Diario Extra reports the jet parking will be ready in about three months, in January, while La Nación gives one year.
- Air movements at the airfield rose from about 6,000 a year in 2017 to 9,129 in 2022, mostly private planes and helicopters linked to the area’s marinas. We could not find a more recent published count.
- An earlier apron award at about US$4.4 million was challenged in April, according to La Nación, and the contractor named at this week’s start order is a different firm. We read that as a reminder that procurement can move.
Chart: Quepos airfield upgrade, reported costs (₡ millions, Sept–Oct 2026)
| Item | ₡ millions | Reported |
|---|---|---|
| Apron (phase 1) | 2,103 | 23 Oct 2026 |
| Terminal (phase 2) | 4,000 | 23 Oct 2026 |
| Total estimate, September | more than 5,000 | 29 Sept 2026 |
| Total estimate, October | more than 6,000 | 23–24 Oct 2026 |
What This Means If You Are Buying
Taxpayers fund this project through the transport ministry, so a buyer pays nothing toward it directly. The question is what it does to the asset you own. The assets most exposed are boutique hotels, villas and rentals within reach of Quepos and the marinas, plus land bought on the promise of a future high-end market. A property that depends on guests arriving by road from San José, which is how most visitors reach the area today, is affected much less.
The useful discipline is to split the spend into what is built and what is not. Using the two reported phase costs, the apron is ₡2,103 million of a combined ₡6,103 million, or 34.5%, and the terminal is ₡4,000 million, or 65.5%. In other words, about two-thirds of the money is for the part that has no contractor yet. The apron mainly gives private jets and helicopters somewhere to park. The terminal is what would make the airfield usable for everyday passengers, and it is the later, less certain piece.
| Milestone | Reported date | Which source says so |
|---|---|---|
| Start of works ordered (apron) | 23 Oct 2026 | La Nación |
| Apron finished | About Oct 2027 (one year) or January 2027 | La Nación says one year; Diario Extra says about three months |
| Terminal tender expected | Around Nov 2026 | La Nación (ministry expectation) |
| Terminal construction starts | Second half of 2027 | La Nación |
| Terminal complete | Late 2028 | La Nación; Diario Extra says 2028 |
Our read, not a forecast: private-jet access can help a small, high-end hotel or villa that already targets that guest, because it shortens a trip for people who do not mind paying for it. It does little for a mid-market rental that competes on price. Dollar figures reported for the project vary with the exchange rate used, so we have kept to colones here.
What Could Go Wrong
- Schedule slip: the terminal has not been tendered, and an earlier apron award was challenged, so the late-2028 date rests on steps that have not happened yet.
- Narrow demand: the traffic growth we found was driven by private aircraft, and most guests will still arrive by road, so a nightly-rate premium may apply to only a small slice of bookings.
- Marketing risk: a seller or broker who prices in “the new airport” is making a claim about the future. Ask for the tender documents and treat any return projection as self-reported and unverified.
- Other constraints: roads, water, power and local permits can limit what you can build or rent regardless of how guests arrive. We did not find verified data on those for this run, so ask for it.
- Title and land status: if a property sits in the coastal maritime zone, its concession status matters far more than any airport. Have a Costa Rican attorney or notary confirm it.
The upside case is real but conditional. If the terminal tender is issued on schedule, a contractor starts in 2027, a scheduled or charter operator announces service, and published air movements rise above the 9,129 recorded for 2022, then higher-spend guests could lift rates for properties that cater to them. Those are the pieces of evidence that would confirm it.
Your Next Steps
- Expat buyers: ask the seller what share of past guests arrived by air and whether the asking price includes an “airport premium”. If it does, ask what the price would be without it.
- Hotel and rental buyers: run your numbers with no airport benefit until the terminal is built, then treat any later premium as upside. Check booking history for the guest type the airport would serve.
- Property owners: keep your current rate assumptions, and note the dates in the table above so you can test them against the ministry’s updates.
- Land buyers: confirm zoning, water and access rights independently of the airport story, with a Costa Rican attorney or notary handling your own transaction.
What to watch next: the transport ministry’s terminal tender, which La Nación says it expects to open around November 2026, and whether the apron is finished in January 2027 or closer to October 2027.
Run Your Own Numbers
Before you credit any property with an infrastructure benefit, write down when it starts, who it serves and what it is worth. A home or rental buyer can fill this in for one property, a lender can use it to haircut collateral value, and a fund allocator can use it to test a sponsor’s business plan.
| Input | Your assumption | Effect on your numbers |
|---|---|---|
| Month the airport benefit starts | ||
| Share of guests who would arrive by air | ||
| Rate premium and the month it begins | ||
| Months you carry the property before the benefit |
Illustration only, not a forecast. This is a hypothetical. Using the reported phase costs, ₡2,103 million plus ₡4,000 million is ₡6,103 million, so the not-yet-tendered terminal is 4,000 ÷ 6,103 = 65.5% of the spend. If a buyer assumed the benefit begins when jet parking opens in January 2027 but the terminal only opens in December 2028 (our reading of “late 2028”), the buyer would wait 23 months longer than assumed.
Questions to take to a sponsor, advisor or counterparty:
- Which part of your projected income depends on the airport, and what happens to the numbers if the terminal opens a year late?
- What share of last year’s bookings came from guests who flew in privately, and can you show it?
- Is the property’s title, water supply and permit status confirmed independently of the airport story?
Resumen en español
- El 23 de octubre el MOPT ordenó iniciar la plataforma del aeródromo de Quepos (₡2.103 millones); la terminal de pasajeros (₡4.000 millones) aún no se ha licitado y se espera para finales de 2028.
- Las fuentes difieren en los plazos (enero de 2027 según Diario Extra, un año según La Nación) y el monto total subió de más de ₡5.000 millones a más de ₡6.000 millones; conviene valorar el plazo más lento.
- Qué vigilar: la licitación de la terminal, prevista para noviembre de 2026. Consulte a un abogado o notario costarricense antes de comprar.
Related reading: Costa Rica’s Electric Train: Why Land Clearing Sets the Schedule, Is a Costa Rica Vacation Rental Still Worth It? Tourism Slows, and our hotel buyer guide.
Data as of 25 October 2026. Figures marked preliminary will be revised. This is general market commentary, not investment advice.
Sources
- La Nación, Quepos airport prepares for more flights (23 Oct 2026)
- Diario Extra, Quepos will have a new airport by 2028 (24 Oct 2026)
- Tico Times, Quepos airport upgrade and new terminal (24 Oct 2026)
- Tico Times, Quepos airfield tender aims to bring private jets (29 Sept 2026)
- Infobae, investments in Quepos and private jets (29 Sept 2026)
- La Nación, Quepos airport transforms to serve private flights (30 May 2026)